Around Northern VirginiaThursday, November 19
Spotsylvania supervisors approve a 550-acre data center campus as Stafford residents push back on another
The 5AM Alexandria team
If you've followed the data center debate south of us, here's where it stands. Spotsylvania County's Board of Supervisors voted 4-3 Tuesday to approve the Crossroads Technology Campus on a 550-acre site near neighborhoods. Supervisor Lori Hayes said the developer agreed to noise mitigation, generator emissions standards, setbacks from homes and no groundwater for cooling.
Spotsylvania supervisors approved the data center campus 4-3
Spotsylvania County Board of Supervisors vote, Nov. 17
4–3
Approve the special use permit for the Crossroads Technology Campus
Yes 4
- McLaughlin
- Hayes
- Mullins
- Frazier
No 3
- Yakabouski
- Lane
- Goosman
Source: WJLA
View as table
| Member | Seat | Vote |
|---|---|---|
| Tim McLaughlin | Yes | |
| Lori Hayes | Yes | |
| Drew Mullins | Yes | |
| Deborah Frazier | Yes | |
| Chris Yakabouski | No | |
| Jacob Lane | No | |
| David Goosman | No |
In Stafford County, residents are pushing back on a proposal near the Rappahannock River. The county's Planning Commission had a public hearing set for Wednesday, Nov. 18.
Stafford's proposed Kings Highway corridor development is enormous
- 37
- data center facilities proposed
- 14
- electrical substations
- 4
- projects along the corridor
- 1,000+
- football fields' worth of area, side by side
Source: FOX 5 DC
- Spotsylvania tax revenue promised: $30 million a year
- Developer guarantees in Spotsylvania: more than 50
- Share of Spotsylvania site that would remain forested: 66%, per Hayes